G and Z can do a work in 12 days (together). G can work alone in 20 days. so how many days it will take Z to finish the work alone?

answer will be 30 days. please show calculation

Respuesta :

Otras preguntas

Which design principle refers to visual equilibrium?
Where is air pollution the worst? coastal areas mountain areas rural areas urban areas
What happens at night with ocean water and the land is cooler than the water? Science
What was most monumental decision in making a trip to Oregon? The season for leaving on the journey The amount of food to take on the journey The type of anima
I use 45 gallons of water per day. What is the average water use in Dec?
What is the sum? 3/x + 4/x(squared)
2 times in 60 seconds how many seconds went by before the manatee surface the first time if it held its breath for the same rate
Ozymandias by Percy Bysshe Shelley I met a traveller from an antique land Who said: “Two vast and trunkless legs of stone Stand in the desert . . . Near them, o
Convert 4 11/19 into an improper fraction A. 34/19 B. 63/19 C. 87/19 D. 44/19
Match the following inner core outer core lower mantle upper mantle (asthenosphere) crust (lithosphere) Very dense liquid of iron and sulfur about 2,250 k