A can do a piece of work in 20 days. He works at it for 5 days, and then B finishes it in 10 more days. In how many days will A and B together finish the work?
a) 5 days
b) 6 days
c) 7 days
d) 8 days

Respuesta :

Otras preguntas

Element ______ has 2 valence electrons and is in period 4.
You are in 3rd place you pass the person in 2nd place, what place are you in?
Hellllllp asapppppppppp
Options: - does not - does
During photosynthesis, plants and some other organisms use energy from the sun to convert carbon dioxide and water into oxygen and sugars. True or false? ; - ;
Alex vende boletos para una obra de teatro escolar .un boleto de adulto cuesta $6.50 y un boleto de estudiante cuesta $4.00. alex vende x entradas para adultos
A magnitude of 1350 pounds of force is needed to stop a block from sliding down a hill whose incline is 17 degrees to the horizontal. what is the weight of the
In this picture, what messages are communicated through touch? It’s really in the class speech but they didn’t have the choice so I put history
please help me with this, thank you so much!!
How would you argue the case of deejay v. the city before the Supreme Court