What is the first phase of the project process?


A. Monitoring


B. Pre-Planning


C. Implementation


D. Planning

Respuesta :

tif21076 tif21076
  • 06-05-2021

Answer:Pre-planning

Explanation:

Answer Link
zlskfrum zlskfrum
  • 06-05-2021

Answer:

Explanation:

Implementation and Monitoring are latter phases of a project.  Pre-planning goes before Planning so the answer is B.

Answer Link

Otras preguntas

Which sentence in this excerpt from Common Sense by Thomas Paine indicates that Great Britain protected the American colonies for mutual gain? But she [Britain]
two square roots of 25 equals
East and West Germans were united in: a. 1990 b. 1991 c. 1992 d. 1993
how do we know that Otzi the Iceman was civilized and intelligent?
Which of the numbers 2, 3, 4, 6 and 9 are factors of 1881?
Hinduism first developed in which part of the world? a. Japan b. Indus River Valley c. China d. Malay Peninsula
What is 324 divisible
X squared minus 25 equals 0
Which of the following is the best example of a check on presidential power
how could you tell if a sample of matter is a element