When building a house, the number of days required to build varies inversely with
with the number of workers. One house was built in 11 days by 49 workers. How
many days would it take to build a similar house with 7 workers?

Respuesta :

myue myue
  • 26-05-2021

Answer: 77 days

Step-by-step explanation:

Answer Link

Otras preguntas

If one inch represents 18 feet, what dimensions would you use to make a scale drawing of a building 630 feet by 450 feet?
Does anyone know how to do this HELP
Look at the diagram above. Label parts of the arch: A, B, and C.
Find the solution for 72 < 7x − 5. 1 x < -11 2 x > 11 3 x > 21 4 x < 11
4/77 = 12/x!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
Question 2In the diagram, BCD is a straight line. AD = 2V3 cmWork out the exact length of CD. Give your answer in the forma + bv3 where a and b are integersNot
Mike is making a nut mixture for an upcoming camping trip. He makes the mixture by combining 1/3 of a cup of cashews and 1/4 of a cup of almonds. If he wants to
which passage shows Francis' feelings about patricia?
If y varies inversely as the square of x and y=2 when x=4.Find x when y=4/5
how many touchdowns did Randy Moss have in 2007