Respuesta :

Аноним Аноним
  • 23-02-2018
kai:
6 days = 1 shed
1 day = 1/6 shed

Mark:
8 days = 1 shed
1 day = 1/8 shed

Together:
1 day = 1/6 + 1/8 shed 

Ans: 1/6d + 1/8d = 1

Answer Link
carlosego
carlosego carlosego
  • 23-02-2018
The first thing you should know is that the rate of each one is:
 Kaitlyn = 1/6
 Mark = 1/8
 Then,
 d = number of days.
 The equation then if they work together is:
 1 / 6d + 1 / 8d = 1
 answer:
 the equation for number of days it would take to build the sheld together is
 1 / 6d + 1 / 8d = 1
Answer Link

Otras preguntas

All the years from A.D. 1400 to A.D. 1499 make up the fifteenth century A.D. true or false?
How does the internal structure of the earth influence the creation of the continents, ocean, and the mountain range
who led the mormons to present day utah in search of religious freedom
what is 5/8 x 24 in simplest form
(√3/2-1/2i)^2 Express in Stanford form a+bi
what connection might exist between global warming and human activities?
The Great Awakening’s religious resurgence served to revive evangelicalism. How can salvation be attained according to evangelicals?
how long has peter randal been an artist
The sum of half a number and two-thirds of the number is less than 14
What is 80 over 100 simplified